Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors

Nuclear Fusion Project Successfully Completed with AFT Fathom™

Applied Flow Technology
AFT

Nuclear Fusion Project Successfully Completed with AFT Fathom™

For decades nuclear fusion has been hailed as the future energy source of humankind – a source of virtually unlimited green energy. Current projects are directed towards fusion research.

Larsen & Toubro Construction (L&T) was responsible for Detailed Design, Engineering, Procurement and Supply of a large cooling water system for a nuclear fusion project being constructed in France. The project specifically focuses on the Component Cooling Water System, which supplies about 100 loops.

M. Arunkumar built an AFT Fathom model of the system. The purpose of the hydraulic study was to determine the optimum pump head of cooling water pumps in order to satisfy outlet pressure requirements for the equipment being cooled. During steady-state hydraulic analysis using AFT Fathom, the cooling water pressure requirement had been met at every outlet except for one piece of equipment.

L&T investigated four options to reduce the cooling water pressure at the pump outlet. These options were modeled as different scenarios in the model. An unexpected outcome from the selected option was used to reduce overall pumping costs by 12%.

The cooling water system consists of plate heat exchangers, horizontal centrifugal pumps, pressurizers, water polishing unit, and equipment that needs cooling; as well as the associated piping, valves and instrumentation. For this particular project, cooling water pressure at the equipment outlet is restricted within certain values for each area that needs cooling.

The steady-state analysis showed the outlet pressure at equipment PSB-129 (Figure 1) was 0.24 MPa-g (35 psig) which was higher than the limited value of 0.1 MPa-g (15 psig). Hence, the challenge was to analyze and reduce the outlet pressure below the maximum pressure limit. In order to reduce outlet pressure, the resistance in the return line had to be reduced.

The Scenario Manager tool enabled Arunkumar to model & check various options to reducing outlet pressure under a single parent scenario. Below are the possible options he determined could reduce the outlet pressure:

  • Option 1: Shifting of heat exchanger to downstream of pumps
  • Option 2: Increased line size of cooling water return line
  • Option 3: Use of booster pumps at outlet of PSB-129
  • Option 4: Shifting of heat exchanger and using a booster pump

Option 4 combined Option 1 & Option 3 and reduced outlet pressure to 0.05 MPag (7 psig), which was within the allowed 0.1 MPag (15 psig). However, it required them to add a booster pump to work with the existing three primary cooling water pumps in order to meet the requirements at PSB-129.

AFT

Figure 2 – Cost variance between initial design condition and design with Option 4.

Adding a booster pump to the design resulted in saving overall pumping cost (Figure 2):

  • 11% reduction in capital pump cost compared to initial design
  • 12% reduction in pump operating cost/day compared to initial design

Using AFT Fathom, L&T construction was able to successfully meet client requirements and reduce their operational costs.

 

Related Articles

Related Whitepapers

Expansion Joint Expertise Improves Industrial Wastewater System Reliability

The majority of industries have wastewater treatment plants. Government agencies and local governments require these facilities to meet pretreatment requirements. Pretreatment rules were enacted to prevent…

How to Decrease Oil Changes with Bearing Isolators [Inforgraphic]

Learning how to decrease oil changes can be time- and money-saving. Oil life can be long if contamination is eliminated, which is easier said than…

Synchronous Machines Are The Optimal Choice For Heavy Industry

TECO-Westinghouse experience assures superior performance and reliability For over a century, Westinghouse has been the pacesetter in the design and production of electric machines for heavy…

Why FLEXXORs Are Designed Differently

J. Hilbert Anderson, President of Coupling Corporation of America, discusses some of the reasons why FLEXXORs are designed differently from all other flexible couplings, and…

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *

Join the #PumpTalk Community


By submitting this form, you are consenting to receive marketing emails from: Empowering Pumps & Equipment, 2205-C 7th Street, Tuscaloosa, AL, 35401, http://www.empoweringpumps.com. You can revoke your consent to receive emails at any time by using the SafeUnsubscribe® link, found at the bottom of every email. Emails are serviced by Constant Contact