Can Steel Mills Save $7 Million a Day through Energized Motor Testing?

ALL-TEST Pro
ATP

Can Steel Mills Save $7 Million a Day through Energized Motor Testing?

 If a steel mill was at risk of losing $5,000 for every minute of unplanned downtime, it would be no surprise to see that steel mill implement a preventive maintenance program to keep their equipment running reliably to avoid unscheduled shutdowns. One American steel manufacturer who understands the importance of preventive maintenance sends their team of motor techs to test motors throughout the steel production facility every 6 months. In April 2014, one motor tech detected a fault in a 100-horsepower Westinghouse AC motor after using the ALL-TEST PRO On-Line II™ energized motor testing instrument.

ALL-TEST ProUnderstanding the Application

This 100HP motor was one of many motors that operated in the #3 Coil Strip, where steel coil is processed through the #3 CAL (Continuous Annealing Line). The annealing line unwinds the steel coils, heats them up to a malleable temperature, and sends it through various processes to achieve specific qualities.

“There are lots of moving parts in a steel plant,” explains Frank Settles, Steel Mill Motor Tech. “When I go out to test motors on a route, I’m testing at least 25 motors at a time.”

Settles connected the portable, hand-held ATPOL II™ energized motor testing instrument to the electrical panel in order to conduct the condition monitoring tests at a safe distance from the operating motor. “When I tested this 100HP motor, the ATPOL II™ indicated there was an issue with the rotor bars,” states Settles.

ALL-TEST ProThe abnormal indications were reported to the department head of the #3 coal strip, and immediate action was taken to replace the motor. Once a new motor was installed in the #3 Continuous Annealing Line, the motor with questionable health was then sent to a Midwestern motor repair facility for further inspection and analysis. The steel mill’s maintenance manager wanted the motor repair facility to check the condition of the motor and confirm the results of the energized motor test.

Further Investigation Confirms ATPOL II™ Test Results

At the motor repair facility, several tests were performed: the 100HP motor showed initial Meg-ohm readings of 200+ at 500-Volts; the surge test was acceptable at 772-Volts; and a growl test was completed on the rotor but showed no abnormalities. Then the rotor was core-tested to look for shorts in the laminations as well as shorts in the connections between the laminations and the grounding ring.

“A hot spot was discovered in the laminations near the short circuiting ring,” explains Jonathan Walma at Harrison Electric, Inc. “The rotor bars have current induced into them from the stator to create a magnetic field. When one of these bars is disconnected, the horsepower that the motor provides is reduced and the current required to operate the motor at full loads increases, so it was a good pull; otherwise the motor would have put itself in an overload situation.”

After the motor repair shop confirmed the rotor issues initially detected by the ATPOL II™, the steel mill’s maintenance manager compared the cost to repair the motor with the cost to purchase a brand new motor. Seeing that the cost to repair the motor was greater than the cost of a new motor, the maintenance manager requested the faulty motor be returned to the steel mill for proper recycling and disposal.

“The steel mill did not suffer any losses because the rotor faults were detected prior to failure,” exclaims Settles. “The ATPOL II™ has been great for finding faults with both AC and DC motors, and I’ve even been able to project ‘down the road’ when there might be an issue with a motor. One time, we had third-party testers come in with different equipment – very expensive, not portable like the ALL-TEST Pro instruments – and they didn’t pick up the issues that the ATP equipment could.” 

Make Motor Testing Part of Your Preventive Maintenance Program

To date, this steel mill has acquired about $80,000 worth of motor testing equipment from ALL-TEST Pro – both energized and de-energized testing instruments. They have regularly upgraded their software, calibrated their equipment, and utilized the on-site and remote support provided by ALL-TEST Pro. This steel mill has made an extensive effort to perform motor testing as part of their preventive maintenance program, and it has resulted in major savings.

So can energized motor testing save every steel mill $7 million per day? While that is a hard question to answer, one thing is for sure – downtime costs money. When equipment fails, it is represented in real dollars every time a production facility stops operating. Make motor testing part of your preventive maintenance program to keep your motors up and running, then calculate the savings.

Watch this video to learn how motor testing can save you time, money, and headaches, or visit www.alltestpro.com for more information.

 

About ALL-TEST Pro LLC

Since 1985, ALL-TEST Pro, LLC has provided industry with the most advanced predictive maintenance testing and troubleshooting tools for AC and DC motors, coils, windings, transformers, generators and more to a wide range of industries worldwide. With a full line of testing instruments, software, accessories and training programs, ALL-TEST Pro has the tools you need to perform advanced non-destructive motor testing and analysis for both de-energized motor circuit analysis and energized electrical signature and power analysis. The extensive capabilities of the instruments, coupled with dependable post-sale training and technical support, ensure improved productivity, reduced downtime and a rapid return on investment.

Author: Richard Scott, General Manager, ALL-TEST Pro, LLC.

Related Articles

ATP

Why Test Motors?

Because Motors Fail! Not all winding faults start as ground faults. Instead, they can start as a weakness in the winding…

Related Whitepapers

Expansion Joint Expertise Improves Industrial Wastewater System Reliability

The majority of industries have wastewater treatment plants. Government agencies and local governments require these facilities to meet pretreatment requirements. Pretreatment rules were enacted to prevent…

How to Decrease Oil Changes with Bearing Isolators [Inforgraphic]

Learning how to decrease oil changes can be time- and money-saving. Oil life can be long if contamination is eliminated, which is easier said than…

Synchronous Machines Are The Optimal Choice For Heavy Industry

TECO-Westinghouse experience assures superior performance and reliability For over a century, Westinghouse has been the pacesetter in the design and production of electric machines for heavy…

Why FLEXXORs Are Designed Differently

J. Hilbert Anderson, President of Coupling Corporation of America, discusses some of the reasons why FLEXXORs are designed differently from all other flexible couplings, and…

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *

Join the #PumpTalk Community


By submitting this form, you are consenting to receive marketing emails from: Empowering Pumps & Equipment, 2205-C 7th Street, Tuscaloosa, AL, 35401, http://www.empoweringpumps.com. You can revoke your consent to receive emails at any time by using the SafeUnsubscribe® link, found at the bottom of every email. Emails are serviced by Constant Contact