Correcting Base Bound and Bolt Bound Conditions in the Shaft Alignment Process-Part 2

Industry Topics
Photo of shaft alignment process

Correcting Base Bound and Bolt Bound Conditions in the Shaft Alignment Process-Part 2

Installing Equipment Properly to Prevent BBBB Conditions from Occurring

The most logical method to prevent alignment problems is to properly install the stationary and movable machines before any piping, duct work, or other attachments are made.

Bear in mind that just because a machine is shipped on a skid assembled does not mean the alignment is suitable (it probably isn’t!). Even on machines that are shipped in an aligned condition, changes can occur during shipping, or while the machine is bolted to a foundation or machine base. This can cause BBBB problems.

Here are some common sense guidelines for minimizing the chance of these conditions.

  • If you receive a skid-mounted machine, set it down in the shop, remove the guard, and check the alignment before ANYTHING ELSE is done to it.  If it is within your alignment tolerance, tag it as “ALIGNED”.
  • If it is not in alignment as received, align it.  This way, both machines can be moved to ensure adequate alignment before installation.
  • To eliminate the risk of a Bolt Bound condition:
    • Loosen hold down bolts in both the stationary and movable machines.
    • Push both machines in the same direction as far as the hold down bolts will allow them to go. Mark the feet positions with a marker.
    • Push both machines in the opposite direction as far as they will go, and mark again.
    • Position both machines mid-way between the marks and bolt down.
    • Perform a rough-in process and align the movable machine to the stationary machine.
    • To eliminate the risk of a Base Bound condition, install shims under each stationary machine foot to raise the height of the stationary machine higher than the moveable machine.
    • Alignment should be re-checked after being bolted down and piped up, or after other accessories are installed. If pipe, duct, or conduit strain moves either machine, it is better to re-align now than after the machine is put into service.
    • In addition, if the machine is mounted to a “green” or partially cured concrete or epoxy base, the alignment should be rechecked after 90 days, to confirm that alignment is still within tolerance.
    • In addition, store the alignment data each time the machine is checked.  This way, you will have conclusive proof that the alignment might have been changed sometime during the installation process.

Related Articles

Sulzer Cost effective sustainable fuel production

Cost effective sustainable fuel production

Benchmarking Market Report highlights cost-leadership of Sulzer Chemtech BioFlux Process Technology for Renewable Fuels production BioFlux® process technology for renewable fuel…

Related Whitepapers

Expansion Joint Expertise Improves Industrial Wastewater System Reliability

The majority of industries have wastewater treatment plants. Government agencies and local governments require these facilities to meet pretreatment requirements. Pretreatment rules were enacted to prevent…

How to Decrease Oil Changes with Bearing Isolators [Inforgraphic]

Learning how to decrease oil changes can be time- and money-saving. Oil life can be long if contamination is eliminated, which is easier said than…

Synchronous Machines Are The Optimal Choice For Heavy Industry

TECO-Westinghouse experience assures superior performance and reliability For over a century, Westinghouse has been the pacesetter in the design and production of electric machines for heavy…

Why FLEXXORs Are Designed Differently

J. Hilbert Anderson, President of Coupling Corporation of America, discusses some of the reasons why FLEXXORs are designed differently from all other flexible couplings, and…

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *

Join the #PumpTalk Community


By submitting this form, you are consenting to receive marketing emails from: Empowering Pumps & Equipment, 2205-C 7th Street, Tuscaloosa, AL, 35401, http://www.empoweringpumps.com. You can revoke your consent to receive emails at any time by using the SafeUnsubscribe® link, found at the bottom of every email. Emails are serviced by Constant Contact